Multiple Locations

Chick-FIl-A

MEP Design

Project Specs

Design Fee

$14,500

Design Time

2 Weeks Each

Construction Duration

9 Months Each

Project overview

Lorem ipsum dolor sit amet, consectetur adipiscing elit

Chick-fil-A, a beloved and widely popular restaurant chain across the United States, entrusted our team with mechanical and plumbing design services for several of their locations. Our contributions encompassed a wide range of tasks, including heating and cooling load calculations, natural gas line sizing (BTU loads), and grease abatement system design. These fast-paced projects required efficient design completion within approximately two weeks, followed by over two months of construction.

 

Natural Gas Heaters

  • Challenge: The contractor wanted to add several natural gas heaters to the drive-thru canopy areas after the main gas line was ran to the canopy location.
  • Response: Our team of mechanical engineers ran through natural gas calculations and determined the line sizing was close to being maxed out.
  • Outcome: The issue was resolved in 1 business day, allowing the project to stay on track.
  • Key Takeaway: Effective communication between the contractor and engineers, paired with quick calculation checks, mitigated the impact of adding equipment that could not be supported.

 

Plumbing/Electrical Clash

  • Challenge: The design documents indicated that both the plumbing pressure reducing assy. and electrical panel occupy the same recessed area within the restaurant.
  • Response: Our plumbing engineers reviewed the area and were able to relocate the pressure reducing assy. To a more manageable location.
  • Outcome: The issue was resolved in 2 business days, allowing the project to stay on track. Drawing revisions were necessary to track changes.
  • Key Takeaway: Effective communication between the contractor and engineers, paired with quick drawing revision, mitigated the impact of any future concerns.

 

General Observations:

  • Both challenges underscore the importance of communication and rapid response mechanisms in construction projects.
  • The durations (1 and 2 business days) reflect a streamlined process, likely supported by strong collaboration among contractors, engineers, and other stakeholders.
  • Common strategies included reviewing engineer developed calculations, flexibility in utility locations, and ensuring solutions were compliant.
Video

Longer detailed heading goes here

Play video
Contact us

Let’s discuss how your community can create capital through energy savings.